About the project
Initiator of the project |
Private investor |
Management |
Management of the Company has a team of professionals, including project implementation specialists and industry experts |
Industry |
Energy |
Purpose of the project |
Project provides for construction and subsequent operation of a cascade of small hydroelectric power plants in the Zhambyl region. |
Project compliance with development goals of the Republic of Kazakhstan |
· Project corresponds to several state programs (State Program of Industrial-Innovative Development of the Republic of Kazakhstan for 2015–2019, “Business Roadmap 2020” program). |
Implementation period: |
2021-2022 |
Location |
Zhambyl region |
Investments |
about KZT 11 billion |
Power |
18.0 MW |
Current status of the project |
• Feasibility study has been developed • Working project has been developed • RSE "Gosexpertiza" report was received • Conclusion of the state environmental expertise was received • Archaeological conclusion was received • Large diameter pipes are purchased • Right on temporary land use is granted. • Technical specifications (TS) for connection to the networks of "ZHES" LLP are received • Agreement for the purchase of electric energy was signed by Financial Settlement Center (FSC KEGOC JSC) • At the moment, work is underway to attract debt and equity financing. |
Fund participation in the Project |
The Fund plans to provide consulting services for raising funds and developing project documentation. |